Oak Bay was supposed to have 258 new homes by now. How many did it build?

A report going to council Monday shows how far Oak Bay is behind the province's housing target, what kind of homes are getting built, and whether the pipeline can close the gap.

Oak Bay was supposed to have 258 new homes by now. How many did it build?
A new house framed around an old oak on Beach Drive in 2007. Photo: pnwra / Wikimedia Commons, CC BY 2.0, cropped.

In September 2023 the province gave Oak Bay a number: 664 net new homes in five years. It also set checkpoints along the way. By September 30 this year, Oak Bay was meant to have 258.

It has 92.

That figure is in the district's Year 3 progress report under the Housing Supply Act, which council receives on Monday, Nov. 23. We read the report and the provincial form behind it. Here is what stands out.

It was still the best year yet

In the 12 months to September 30, 73 homes in Oak Bay received occupancy permits and 17 were demolished. That leaves 56 net new homes, more than the previous two reporting years combined (36).

Staff point to the zoning bylaw. Secondary suites, allowed since 2022, drove the first two years. This year most of the new supply came from the small-scale multi-unit housing rules added in July 2024. The report notes the lag between changing the rules and seeing finished homes.

Bigger homes, and a few firsts

34 of the 56 net new homes have three bedrooms. In earlier years, one-bedroom units led.

Year 3 also brought the first duplexes, triplexes and fourplexes completed since the target order arrived. The triplexes and fourplexes were built as townhouses. Secondary suites and single-family houses are still the most common types overall.

What is not getting built

None of the homes completed this year were purpose-built rentals, and none were below-market rentals. Across all three years, the below-market count is zero.

The province's guidelines for Oak Bay call for 141 below-market rental homes over the five years. Of the 58 net new rental homes since 2023, 47 are secondary suites.

Can Oak Bay catch up by 2028?

The five-year target is 664 by September 30, 2028. Staff count 362 homes in the pipeline:

  • 193 already approved through rezoning, development permits or building permits
  • 101 in planning applications under review
  • 68 in building permit applications under review

The largest single project is a 118-unit Camosun College student housing building, which has an approved building permit and is scheduled for 2028.

By our count, if every one of those 362 homes were finished in time, Oak Bay would reach 454. That is about 210 short of the target.

The report says much of what decides housing supply, such as construction costs, financing and demand, is largely outside the district's control. It lists the work under way: a $335,000 project to speed up approvals, with $200,000 of it from a provincial grant; a district-wide infrastructure study due early in 2027; and a rewrite of the zoning bylaw, including possible pre-zoning for townhouses and apartments, due late in 2027.

What happens to a town that misses? The provincial reporting form says only that the minister "may initiate compliance action as set out in the Act."

Watch Monday's meeting

Council meets Monday, Nov. 23 at 7 pm at Municipal Hall, 2167 Oak Bay Avenue, and on Zoom. The housing report is on the agenda for information, so there is no vote on it. Meetings stream live on the district's video page.